(updated each month)
January 2012
Works are nearing completion - the pool is almost ready for filling, all beach front cottages are complete, restaurant and bar ready, and the pool side rooms only have interior works remaining.

Inside of an A/C beach cottage with extra bed Roof of cottage

Cottage Balcony Beach

Pool is nearly there Restaurant needing furniture

Beach Main Building
December 2011
Plenty going on this month as some friends came to stay and it gave an opportunity to train some of the staff. The weather was great and the opening will be early February 2012.


November 2011
Not many construction photos as much of the work is in the ground but here are a few general photos that show that completion is getting closer.

Beach bungalows are nearing completion


October 2011
Finally the rains abated and the sun shone again. The sea and sky are amazing shades of blue.



August/September 2011 - More Rain
The rains continued and progress was slower than hoped, but we now have 4 beach front bungalows at the final fitting out stage, three two story pool side villas up to first floor level, the staff accommodation has started and landscaping is taking shape.

Landscaping starts and it's now looking like a resort

Two story pool-side villa taking shape The pool is just waiting for the tiles

The beach at dusk View from the bar

The main building from the pool
July 2011-The month of rain
July was a month of heavy rain, but the prototype was completed and other single story units were progressing well.

The Roof has a glazed center panel so you can look up at the stars from the bed.
June 2011 - Ian's visit to site

Sunset at Cashew Grove The Main Restaurant / Bar
Roof Trimming Roof Details

First Bungalow Takes Shape The end of a day - 1 shot of Rum & Coke
More photos can be found here: Ian's visit on Photobucket
May 2011- First signs of a resort
The nursary has many colourful plants sprouting and the masonry block fabrication line is producing 100 blocks per day.
A few photos of progress during May.

The Masonry Factory The Pool is almost complete

The First Bungalow Construction Crew

The Nursery Collecting Thatch
April 2011 - Construction Starts
Construction finally started in April with Bill moving to Busuanga, buying a little truck and setting up camp on the resort site it Cheey.
During the month there was plenty of activity with all the systems being put in place. Bamboo treatment plant erected to ensure the bamboo will last, block making factory established to save the transportation from Manila, site office erected, nursery established to grow the plants needed for the gardens, and generator installed. All is set to start the construction of the first prototype hut during May.Below are a few photos of the installations.

The banca on the beach Setting up camp

Interviewing the first workers The little Billandian truck

Preparing the landscape gardens in the nursery Bamboo Treatment Plant is installed

Gererator House and Store Block Making Factory

The site office located behind Bill's camp Excavation for the pool started