A Record of the Construction Progress
(updated each month)

January 2012


Works are nearing completion - the pool is almost ready for filling, all beach front cottages are complete, restaurant and bar ready, and the pool side rooms only have interior works remaining.

 

         Inside of an A/C beach cottage with extra bed                                            Roof of cottage

 

                       Cottage Balcony                                                           Beach

 

                   Pool is nearly there                                                     Restaurant needing furniture

 

                                    Beach                                                                 Main Building


December 2011

Plenty going on this month as some friends came to stay and it gave an opportunity to train some of the staff. The weather was great and the opening will be early February 2012.

  


 

  



November 2011

Not many construction photos as much of the work is in the ground but here are a few general photos that show that completion is getting closer.

  

Beach bungalows are nearing completion

 

 


October 2011

Finally the rains abated and the sun shone again.  The sea and sky are amazing shades of blue.







August/September 2011 - More Rain

The rains continued and progress was slower than hoped, but we now have 4 beach front bungalows at the final fitting out stage, three two story pool side villas up to first floor level, the staff accommodation has started and landscaping is taking shape.

  

Landscaping starts and it's now looking like a resort


  

                 Two story pool-side villa taking shape                            The pool is just waiting for the tiles


  

                          The beach at dusk                                                            View from the bar



The main building from the pool
 


July 2011-The month of rain

July was a month of heavy rain, but the prototype was completed and other single story units were progressing well.


 

The Roof has a glazed center panel so you can look up at the stars from the bed.



June 2011 - Ian's visit to site

Ian visited Cashew Grove for two weeks and joined Bill in supervising the work and deciding on a few design details.

 
                       Sunset at Cashew Grove                                                 The Main Restaurant / Bar

  
                                Roof Trimming                                                            Roof Details

 
                         First Bungalow Takes Shape                                   The end of a day - 1 shot of Rum & Coke

More photos can be found here:    Ian's visit on Photobucket


May 2011- First signs of a resort

The first phase of construction is now underway, with site installation complete, the pool is dug, foundations to main building well underway and the first Type B Bungalow has its frame erected.

The nursary has many colourful plants sprouting and the masonry block fabrication line is producing 100 blocks per day.

A few photos of progress during May.

 
                            The Masonry Factory                                                          The Pool is almost complete

   
                            The First Bungalow                                                          Construction Crew

  
             
  The Nursery                                                                               Collecting Thatch

 

April 2011 - Construction Starts

Construction finally started in April with Bill moving to Busuanga, buying a little truck and setting up camp on the resort site it Cheey.

During the month there was plenty of activity with all the systems being put in place.  Bamboo treatment plant erected to ensure the bamboo will last, block making factory established to save the transportation from Manila, site office erected, nursery established to grow the plants needed for the gardens, and generator installed.  All is set to start the construction of the first prototype hut during May.

Below are a few photos of the installations.

               The banca on the beach                                                                           Setting up camp

    
            Interviewing the first workers                                                  The little Billandian truck

 
     Preparing the landscape gardens in the nursery                                          Bamboo Treatment Plant is installed


 
             Gererator House and Store                                                                                                    Block Making Factory

 
    The site office located behind Bill's camp                  Excavation for the pool started